Rompetrol installs 11 ultra-fast charging stations for electric vehicles

Green Forum
An eMobility project, worth about €2.2 million, co-financed by the European Union through the CEF Transport Facility, will be implemented in Romania by KMG Rompetrol Development. The project will be implemented by November 9, 2025.

KMG Rompetrol Development submitted in November 2022 an application for funding for a project on the acquisition and installation of ultra-fast charging stations for electric vehicles. These will be located in Rompetrol fuel stations located in existing integrated service centers on the A1 motorway, an important section of the Trans-European Transport Network (TEN-T). 

The project "Rompetrol's development of alternative fuel infrastructure on the A1 motorway at the RO-HU border" is co-financed by the European Union through the European Interconnection Facility for Europe (CEF-Transport), approved on 15 March 2023 by the European Climate, Infrastructure and Environment Executive Agency.

The project aims to install 11 300 kW charging stations  (each station with two 150 kW charging points) and to upgrade the grid connection for 11 locations with a power of 600 kW each in CNAIR1 locations as follows:  

1.A1 motorway, km 558+380, lot 1 Right – Pecica, Arad county

2.A1 motorway, km 558+380, lot 1 Left – Pecica, Arad county

3.A1 motorway, km 530+536, lot 2 Right – Sagu, Arad county

4.A1 motorway, km 530+536, lot 2 Left – Sagu, Arad county

5.A1 motorway, km 500+596, lot 3 Right – Giarmata, Timiș county

6.A1 motorway, km 500+596, lot 3 Left – Giarmata, Timiș county

7.A1 motorway, km 481+646, lot 4 Right – Recaş, Timiș County

8.A1 motorway, km 481+646, lot 4 Left – Recaş, Timiș county

9.A1 motorway, km 340+500, lot 8 Right – Orastie, Hunedoara County

10.A1 motorway, km 340+500, lot 8 Left – Orastie, Hunedoara county

 11.A1 motorway, km 260+160, lot 11 Right – Cristian, Sibiu county

The total estimated value of the project is approximately €2.2 million, of which approximately €900,000 will be provided by the European Union. 

RECOMMENDED
RECOMMENDED FROM THE HOME PAGE
Microsoft hits 100% renewable energy target five years early
Energy

Microsoft hits 100% renewable energy target five years early

Microsoft has achieved its goal of matching 100% of its annual global electricity consumption with renewable energy, reaching the milestone five years ahead of its 2025 target. The achievement supports the company's commitment to become carbon negative by 2030.

Real estate

How is EU real estate navigating the CSRD changes? Take our survey

The recent weakening of the CSRD may have some real estate developers cheering the compliance rollbacks, but the consequences could be complicated. A new research survey examines how EU real estate firms are navigating changes to the CSRD, and what that could mean for upcoming SFDR revisions.

Energy

Waldevar Energy builds utility-scale PV parks in Romania

Waldevar Energy has begun construction on two utility-scale photovoltaic parks for Doral Energy in Tudor Vladimirescu (Brăila County) and Ștefan Vodă (Călărași County), Romania. The projects will deliver 14 MWp of installed capacity using around 25,000 photovoltaic panels.

Industry

Lidl Romania exceeds 2030 sustainability targets early

Lidl Romania has published its eighth sustainability report for the 2024 financial year, announcing accelerated progress in reducing environmental impact. The retailer has achieved its international 2030 target for transitioning to natural refrigerants, with these now used in 100% of logistics centres and 81.7% of stores, compared to the original goal of 100% of logistics centres and 40% of stores. The company has also increased its green energy usage to 80% of total consumption.

READ MORE
Green Forum  |  19 February, 2026 at 10:24 AM
Green Forum  |  5 February, 2026 at 11:47 PM