Europe adds 6.4 GW of wind capacity in H1 2024

Green Forum
WindEurope's Autumn Wind Energy Data shows Europe built 6.4 GW of new wind farms in the first half of 2024. 

Turbine orders were up year on year and auction volumes are strong. But grid bottlenecks are delaying projects. And it's challenging right now to get big new investments over the line. Further improvements are needed in auction design. Permitting is improving though not everywhere yet. And ports need investments.

New wind installations in H1 2024

In the first half (H1) of 2024 Europe added 6.4 GW of new wind energy capacity: 5.3 GW onshore and 1.1 GW offshore. The EU-27 built 5.7 GW of this: 4.7 GW onshore and 1 GW offshore. Germany built the most with 1.7 GW, followed by France (1.2 GW) and Spain (876 MW).

Europe now has 278 GW of wind power capacity. 242 GW of this is onshore and 35 GW offshore. The EU-27 now has 225 GW of wind: 205 GW onshore and 20 GW offshore.

Wind turbine orders are up on last year: by 11% on H1 2023 for all of Europe and by 33% for the EU. And current auction volumes are strong: EU Governments awarded 19.7 GW of new wind capacity in their auctions in H1, twice as much as in H1 2023. The permitting numbers are also encouraging, notably the 5 GW new onshore permits Germany awarded in H1.

But investment decisions to build new wind farms are down on last year. Europe took €15.4bn of final investment decisions (FIDs) in new wind farms in H1 2024. This is less than 30% of the total FIDs taken in 2023. There are four offshore FIDs so far this year. The new installations in H1 2024 are slightly less than expected, and less than half of what was built in the whole of 2023. We now expect the EU to build 15 GW of new wind farms this year, compared to 16 GW in 2023.

RECOMMENDED
EIB and Commerzbank strengthen Europes wind industry
Industry

EIB and Commerzbank strengthen Europe's wind industry

The European Investment Bank (EIB) is using again its €5 billion initiative to support manufacturers of wind-energy equipment in Europe by extending a €500 million counter-guarantee to Germany-based Commerzbank AG.

RECOMMENDED FROM THE HOME PAGE
Microsoft hits 100% renewable energy target five years early
Energy

Microsoft hits 100% renewable energy target five years early

Microsoft has achieved its goal of matching 100% of its annual global electricity consumption with renewable energy, reaching the milestone five years ahead of its 2025 target. The achievement supports the company's commitment to become carbon negative by 2030.

Real estate

How is EU real estate navigating the CSRD changes? Take our survey

The recent weakening of the CSRD may have some real estate developers cheering the compliance rollbacks, but the consequences could be complicated. A new research survey examines how EU real estate firms are navigating changes to the CSRD, and what that could mean for upcoming SFDR revisions.

Energy

Waldevar Energy builds utility-scale PV parks in Romania

Waldevar Energy has begun construction on two utility-scale photovoltaic parks for Doral Energy in Tudor Vladimirescu (Brăila County) and Ștefan Vodă (Călărași County), Romania. The projects will deliver 14 MWp of installed capacity using around 25,000 photovoltaic panels.

Industry

Lidl Romania exceeds 2030 sustainability targets early

Lidl Romania has published its eighth sustainability report for the 2024 financial year, announcing accelerated progress in reducing environmental impact. The retailer has achieved its international 2030 target for transitioning to natural refrigerants, with these now used in 100% of logistics centres and 81.7% of stores, compared to the original goal of 100% of logistics centres and 40% of stores. The company has also increased its green energy usage to 80% of total consumption.

READ MORE
Green Forum  |  19 February, 2026 at 10:24 AM
Green Forum  |  5 February, 2026 at 11:47 PM